Approval of drawings

Application for approval of drawings in respect of newly established Master Unit sub-stations, switching stations, Master Receiving stations, Transmission Lines, Inter linking lines and UG cable laying of supplier installation and IPPs, Co-Gen, CPPs and MSB of 24 meters of height & above shall be submitted to the Chief Electrical Inspector to Govt. (CEIG), Bangalore and consumer installations of LT, HT, MSB of 15m and above & DG set installation shall be submitted to the Jurisdictional offices of Electrical Inspectorate as per the Delegation of powers (DOP) To view Delegation Of Powers click here) with all the relevant drawings and details as listed below for the particular category of installation
Click here for the step by step procedural flow for Approval of Electrical Drawing at Head Office
Click here for the step by step procedural flow for Approval of Electrical Drawing at Field Office

Common Documents:

  1. Application in Form-1 duly signed by the applicant or his GPA holder (along with copy of relevant document such as JDA/GPA etc.); in case of supplier/licensee installations not below the rank of The Assistant Executive Engineer or its equivalent.
  2. Prescribed drawing scrutiny fees paid challan or Receipt.
  3. Copy of valid License of the Electrical Contractor, Supervisor and; Wireman permit copy Endorsed to concerned LEC
  4. Affidavit-8 : Authorization of owner of the installation to the Licensed Electrical Contractor on Rs 20 /- Stamp paper
  5. Form Z: estimate and agreement made with the Licensed electrical Contractor and consumer on Rs 200/- stamp paper
  6. Copy of proof of property ownership/occupancy document.

EHT Installations:

  1. Copy of power sanction letter from licensee along with sketch and estimate

HT Installations:

  1. Copy of power sanction letter from licensee along with sketch and estimate

TC/DCW Installations:

  1. Copy of power sanction letter from licensee along with sketch and estimate
  2. In case of layouts copy of layout sanction plan from competent authority.

Terminal Bay extension:

  1. Copy of power sanction letter from licensee along with sketch and estimate

 

EHV/ HV Line/Cable Installations:

  1. NOC from Railways, NOC from national highway, PTCC approval, NOC from Air port authority etc. and ROW documents (if applicable)
  2. Check survey report along with tower schedule for transmission and power evacuation lines & approved topo-map (for 33kV and above)

LT Loads:

  1. Approval copy & approved drawings of existing installation where additions/alterations of Installation is proposed.
  2. In case applicant is not the owner, consent from the owner of the installation.

Temporary Installation:

  1. Temporary power sanction letter by ESCOMS.

DG Set Installations:

  1. In case applicant is not the owner, consent from the owner of the installation.
  2. Approval copy of existing installation along with ESCOM RR No. (if applicable).

Solar Installations:

  1. In case applicant is not the owner, consent from the owner of the installation.

Approval copy of existing installation along with ESCOM RR No. (if applicable).and

×